Restoration of lath and plaster walls in Main chapel
Mr. Bruce Evans offered to skim coat and repair the original lath and plaster walls of the main chapel. Vestry accepted his proposal. The project started on October 9, 2023. The south wall was completed first. The east wall was repaired, then skim coated. Adam Sutton was hired by Mr. Evans to assist in assembling scaffold, removal of sagging lath and plaster, and trash removal.